Final answer:
An appropriate estimate of the standard deviation for the length of time to complete a computer project, using the range rule of thumb, would be 7.5 hours.
Step-by-step explanation:
The computer science department wants to estimate the average length of time to complete a computer project with a precision of within 5 hours and a confidence level of 0.96.
Without an existing estimate of the standard deviation, we can use the range rule of thumb for standard deviation, which suggests that the standard deviation (σ) can be approximated as the range divided by 4.
Given that the shortest time is 6 hours and the longest time is 36 hours, the range is 36 - 6 = 30 hours.
Therefore, an appropriate estimate of the standard deviation would be 30 hours / 4 = 7.5 hours.