Final Answer:
True. When multiple teams are working on a project in an Agile framework, they should select work from the same Product Backlog, fostering collaboration and alignment towards the overall project goals.
Step-by-step explanation:
In Agile methodologies, especially in frameworks like Scrum, it is true that multiple teams working on a project should pull items from the same Product Backlog. The Product Backlog represents the prioritized list of features, user stories, or tasks that need to be addressed in the project. By having a shared Product Backlog, teams ensure alignment with the overall project vision and goals. It promotes transparency, collaboration, and a unified understanding of the work that needs to be done. Each team, during their sprint planning, selects items from this common backlog to work on, contributing to the integrated development effort.
Option B is the answer.