Final answer:
The net present value of the project is $7,555.96. The project should be undertaken.
Step-by-step explanation:
To calculate the net present value (NPV) of the project, we need to discount each cash flow at the cost of capital and sum them up. The formula to calculate the present value of a cash flow is PV = CF / (1+r)^n, where PV is the present value, CF is the cash flow, r is the discount rate, and n is the number of years. Applying this formula to the cash flows provided and discounting them at 11 percent, we get:
- Year 1: $41,000 / (1+0.11)¹ = $36,936.94
- Year 2: $50,000 / (1+0.11)² = $39,340.18
- Year 3: $43,000 / (1+0.11)³ = $31,271.93
- Year 4: ($50,000) / (1+0.11)⁴ = ($33,661.73)
- Year 5: $92,000 / (1+0.11)⁵ = $58,668.64
Next, we sum up these present values: $36,936.94 + $39,340.18 + $31,271.93 + ($33,661.73) + $58,668.64 = $132,555.96. The net present value is the sum of the present values minus the initial investment, which is $132,555.96 - $125,000 = $7,555.96. Hence, the net present value of the project is $7,555.96.
Considering the net present value is positive, the project should be undertaken as it is expected to generate a positive return.