Natasha and the team have now finalized their goals and objectives and have completed a detailed step-by-step schedule and timeline to follow in order to complete the project on time. However, the design team has exceeded their delivery date for the final design documents for the product. What can Natasha do to resolve this issue and move the project forward? A.Go to the management team and tell them the design team is not doing their job. B.Continue to move forward in the development plan without their input. C.Change the timeline to extend the deadline for the additional amount of time needed. D.Meet with the design team to determine what is needed to complete their part of the project.

1 Answer

6 votes

Answer:

D. Meet with the design team to determine what is needed to complete their part of the project.

Step-by-step explanation:

In this situation, it is essential to address the issue with the design team directly and work collaboratively to understand the challenges they are facing. Meeting with the design team can help identify any obstacles, resource constraints, or issues that are causing the delay. Once the root causes are identified, Natasha and the team can work on solutions, whether it involves reallocating resources, adjusting the timeline, or finding other ways to support the design team in completing their part of the project. Open communication and problem-solving with the design team are likely to lead to a more effective resolution and moving the project forward.

User Max Makhrov
by
7.0k points