Final answer:
To draw the PERT network, identify dependencies and create the network. Prepare the activity schedule by calculating earliest and latest times. Determine the critical path. The project cannot be finished within the 30-week deadline.
Step-by-step explanation:
To draw the PERT network for the project, we need to identify the activities and their dependencies. From the given information, we can create the following network:
To prepare the activity schedule, we need to determine the earliest start time (ES), earliest finish time (EF), latest start time (LS), and latest finish time (LF) for each activity. Using the PERT network, we can calculate these times:
The critical path is the longest path from the start node to the end node in the network. In this case, the critical path is A - B - F - H, with a duration of 35 weeks. Any delay in activities on the critical path will delay the overall project.
To find the probability that the project will be finished within the 30-week deadline, we can use the concept of critical path. Since the critical path duration (35 weeks) is greater than the deadline (30 weeks), it is not possible to finish the project within the time limit.