24 workers can do a piece of work in 10 days how many workers should be added to complete the work in 8 days​

User Ascandroli
by
7.8k points

1 Answer

5 votes

Answer:

Add 6 workers

Explanation:

Simple rule of three:

workers. days

24. 10

X. 8

X = (24 * 10)/8

X = 30 (total workers to complete the work in 8 days)

30 - 24 = 6 workers more.