Nathan and Matt plan to paint a house. If Nathan works alone, it will take 10 days. If Matt works alone, it will take 15 days. How many days will it take to finish the job if they work together?
asked
Jan 21, 2022
48.6k
views
21
votes
Nathan and Matt plan to paint a house. If Nathan works alone, it will take
10 days. If Matt works alone, it will take 15 days. How many days will it
take to finish the job if they work together?
Mathematics
high-school
EaranMaleasi
asked
by
EaranMaleasi
4.3k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
7
votes
Nathan= 1/10 of the job per day
Matt= 1/15 of the job per day
3/30 + 2/30. =5/30
1/(5/30) = 30/5. Or 6 days for both working together.
Lloyd Macrohon
answered
Jan 27, 2022
by
Lloyd Macrohon
4.2k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
4.4m
questions
5.7m
answers
Other Questions
Before beginning voice lessons, Aubrey already knew how to sing 357 pieces, and she expects to learn 2 new pieces during each week of lessons. After 78 weeks of voice lessons, how many pieces will Aubrey
A study was completed in Florida. In southern Florida, the study involved 3,000 patients; 54% of them experienced flulike symptoms during the same month. The study had a margin of error of 1.8%. What does
Solve for x in the equation 3 x squared minus 18 x + 5 = 47. (I need this to be an answer like X=3+\_ square root 23)
Please answer asap.......... ...
Can someone help me plz I have to Turn 27/9 in simplest
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org