As discount rate increases, NPV of a simple project:

Select one:
a. Decreases at an increasing rate
b. Decreases at a steady rate
c. Decreases at a decreasing rate
d. Increases at a decreasing rate

User Ervin
by
7.7k points

1 Answer

1 vote
B is the correct answer for it