93.2k views
5 votes
The number of days, D, to complete resarch is inversely proportional to the number of resaerchers, R, who are working. The research takes 125 days to complete with 16 people working on it. How many people are needed for 40 days?

User Mawaheb
by
7.6k points

1 Answer

2 votes

Answer:

50 people

Explanation:

Given a research project that take 16 people 125 days to complete, you want to know the number of people needed to complete the project in 40 days.

People-days

In math, project effort is measured in people×days. That value is considered to be a constant for a given project. This makes the number of people inversely proportional to the number of days, and vice versa.

(16 people)×(125 days) = 2000 people·days = (p people)×(40 days)

Dividing by 40 days, we have ...

p people = (2000 people·days)/(40 days) = 50 people

50 people are needed to complete the research in 40 days.

__

Additional comment

In real life, more people may get in each other's way. Or too few people may cause motivation, cooperation, and synergy to be lost. The maxim, "adding people to a late project makes it later" has a certain basis in reality.

User Yongjieyongjie
by
6.8k points