223k views
2 votes
To make 150 telephones, ComTech, Inc. had these manufacturing costs: materials $1,282.29; labor, $1,975.26; factory overhead, $1,234.31. What was the prime cost of making the

telephones? What was the total manufacturing cost of each phone. on average. to the nearest whole cent

User Luiz Geron
by
7.8k points

1 Answer

1 vote

Answer:

The prime cost of making the 150 telephones is the total cost of materials and labor, which is $3,257.55. The total manufacturing cost of each phone, on average, is $21.72 to the nearest whole cent. The factory overhead cost of $1,234.31 is spread out over all of the telephones and is not factored into the prime cost

Step-by-step explanation:

User Sithu
by
8.2k points