Answer:
To prepare the job order cost sheets for Job 1 and Job 2, we need to calculate the direct materials, direct labor, and overhead costs for each job. The job order cost sheet will then show the total cost incurred for each job.
Job 1:
Direct materials:
Requested materials = $375
Direct labor:
18 hours worked x $23 per hour = $414
Overhead:
18 hours worked x $20 per hour = $360
Total cost:
Direct materials + Direct labor + Overhead = $375 + $414 + $360 = $1,149
Therefore, the job order cost sheet for Job 1 would be:
Job 1
Direct Materials: $375
Direct Labor: $414
Overhead: $360
Total Cost: $1,149
Job 2:
Direct materials:
$780 total direct materials - $375 used for Job 1 = $405
Direct labor:
29 hours worked x $23 per hour = $667
Overhead:
29 hours worked x $20 per hour = $580
Total cost:
Direct materials + Direct labor + Overhead = $405 + $667 + $580 = $1,652
Therefore, the job order cost sheet for Job 2 would be:
Job 2
Direct Materials: $405
Direct Labor: $667
Overhead: $580
Total Cost: $1,652
Step-by-step explanation: