If 4 men, each working an 8-hour day, have to complete 224 hours of work, then the number of days required to complete the work is:
Total number of hours of work / Number of hours of work done by 4 men in a day
= 224 / (4 x 8)
= 7
So, it will take 4 men, each working an 8-hour day, 7 days to complete the project.
II. Each of the 4 men will work for 7 days, and each man works 8 hours a day. So, the total number of hours worked by all the men is:
Total number of men x Total number of days x Number of hours worked by each man per day
= 4 x 7 x 8
= 224 hours
Therefore, the total cost of employing all 4 men is:
Total number of hours x Rate per hour
= 224 x $57.50
= $12,880
III. If the 4 men have to complete the project in 4 days, then the number of hours of work they have to do each day is:
Total number of hours of work / Total number of days to complete the project
= 224 / 4
= 56 hours
Each man works 8 hours a day, so the total number of hours of overtime they have to put in per day is:
Number of hours of work per day - Number of hours worked by each man per day
= 56 - 8
= 48 hours
Therefore, each man must put in 6 hours of overtime per day to complete the project in 4 days.
IV. If the overtime rate of payment is l times as much as the regular hourly rate, then the overtime rate of payment is:
l x $57.50
= $57.50l
Let the overtime rate of payment be $r per hour. Then:
r = $57.50l
The cost of the project is the sum of the cost of regular hours and the cost of overtime hours. The cost of regular hours is:
Number of regular hours x Regular hourly rate
= 4 x 8 x 7 x $57.50
= $16,240
The cost of overtime hours is:
Number of overtime hours x Overtime hourly rate
= 4 x 6 x 7 x $57.50l
= $12,180l
So, the total cost of the project is:
Total cost = Cost of regular hours + Cost of overtime hours
= $16,240 + $12,180l