Answer:
The answer is below
Step-by-step explanation:
Let x represent the number of railroad cars of scrap purchased per day from Atlanta and let y represent the number of railroad cars of scrap purchased per day from Birmingham.
Since Atlanta yields 1 ton of copper and 1 ton of lead while Birmingham yields 1 ton of copper and 2 tons of lead.
The foundry needs at least 2.5 tons of copper per day. Hence:
x + y ≥ 2.5 (1)
The foundry needs at least 4 tons of lead per day. Hence:
x + 2y ≥ 4 (2)
Plotting equations 1 and 2 using geogebra online graphing tool, we get the points that is the solution to the problem as:
(0, 2.5), (4, 0), (1, 1.5)
Car from Atlanta cost $10000 while car from Birmingham costs $15000. Therefore the cost equation is:
Cost = 10000x + 15000y
We are to find the minimum cost:
At (0, 2.5): Cost = 10000(0) + 15000(2.5) = $37500
At (4, 0): Cost = 10000(4) + 15000(0) = $40000
At (1, 1.5): Cost = 10000(1) + 15000(1.5) = $32500
The minimum cost is at (1, 1.5).