If a 4 men can finish a job in 6 day how long would it take 3men to finish the job, working at the same rate

User AWS PS
by
7.6k points

1 Answer

0 votes

Answer:

It would take 3 men working at the same rate 8 days to finish the job that 4 men can finish in 6 days.

Explanation:

To solve this problem, we can use the formula:

(time 1) x (number of people 1) = (time 2) x (number of people 2)

Let's plug in the given values:

(6 days) x (4 men) = (time 2) x (3 men)

Simplifying this equation, we can solve for the unknown variable (time 2):

time 2 = (6 days x 4 men) / (3 men)

time 2 = 8 days

Therefore, it would take 3 men working at the same rate 8 days to finish the same job that 4 men can finish in 6 days