Answer:
Step-by-step explanation:
The critical path is the longest path through a project network diagram, which includes all the activities that are critical to the completion of the project. In order to calculate the critical path, you will need to follow these steps:
Identify all the activities that need to be completed for the project.
Determine the duration of each activity. This can be estimated based on past experience or expert opinion, or by conducting time studies.
Create a network diagram that shows the sequence of activities and their dependencies. This can be done using software such as Microsoft Project or by drawing a diagram manually.
Identify the earliest start and finish times for each activity, based on the dependencies and durations.
Identify the latest start and finish times for each activity, based on the project deadline.
Calculate the total float or slack for each activity, which is the amount of time that an activity can be delayed without affecting the overall project completion date.
Identify the critical path, which is the longest path through the project network diagram that has zero total float or slack. This means that any delay in one of the activities on the critical path will cause a delay in the overall project completion date.
Once you have identified the critical path, you can focus your attention on managing and monitoring the activities on that path to ensure that the project stays on schedule.