Answer: See Explanation
Step-by-step explanation:
The payback period for both projects would be calculated as:
Alpha Project
Cost = $530,000
Annual net cash flow = $60,000
Payback period = Cash / Annual net cash flow
= $530,000 / $60,000
= 8.83
Beta Project
Cost = $170,000
Annual net cash flow = $18,000
Payback period = Cash / Annual net cash flow
= $170,000 / $18,000
= 9.4
We can see that Alpha Project is better as the payback period is lesser than Beta project