108k views
5 votes
Which of the following is NOT included in Cost of Quality?

a.
Operating computers required for the project.

b.
Preventing nonconformance to requirements.

c.
Failing to meet requirements (rework).

d.
Appraising the product or service for conformance to requirements.

1 Answer

6 votes

Answer:

A. Operating computers required for the project.

Step-by-step explanation:

User Iba
by
7.3k points