Answer:
≈$13,315.20
Step-by-step explanation:
Before the acceleration, the crew of 6 workers worked 40 hours per week, for a total of:
6 workers × 40 hours/worker/week = 240 hours/week
The project was expected to take 11 weeks, for a total of:
11 weeks × 240 hours/week = 2,640 hours
The cost of labor for the original schedule would be:
240 hours/week × $20/hour/worker × 6 workers = $28,800/week
Over 11 weeks, this would be a total labor cost of:
$28,800/week × 11 weeks = $316,800
Now, with the accelerated schedule, the workers will work an extra 8 hours on Saturdays, for a total of:
6 workers × 8 hours/worker = 48 hours
On Saturdays, the workers will be paid time-and-a-half, which means they will be paid $30 per hour (1.5 times the normal rate of $20 per hour).
So the labor cost for each worker on Saturdays will be:
$30/hour/worker × 8 hours/worker = $240/worker
For the whole crew, the labor cost for Saturdays will be:
$240/worker × 6 workers = $1,440/week
So the new total labor cost per week will be:
240 hours/week × $20/hour/worker × 6 workers + $1,440/week = $30,240/week
To calculate the revised expected duration of the project, we need to divide the total number of hours required for the project by the total number of hours worked per week, including the Saturday overtime:
2,640 hours ÷ (240 hours/week + 48 hours/week) = 9.23 weeks
So the revised expected duration of the project is approximately 9.23 weeks.
The added cost due to the acceleration is the difference between the total labor cost for the original schedule and the total labor cost for the accelerated schedule:
$30,240/week - $28,800/week = $1,440/week
Over the 9.23 weeks of the accelerated schedule, this added cost will be:
$1,440/week × 9.23 weeks = $13,315.20
So the added cost due to the acceleration is approximately $13,315.20.