86.9k views
5 votes
Allocation is the portion of a resource's capacity devoted to work on a task. Every resource is said to be in one of 3 states of allocation, which are:

OA. Under allocated, Totally allocated or Over allocated
OB. Not allocated, Fully allocated or Over allocated
OC. Under allocated, Fully allocated or Super allocated
D. Under allocated, Fully allocated or Over allocated

User Timmerz
by
7.7k points

2 Answers

2 votes

Answer:

D. Under allocated, Fully allocated or Over allocated

Step-by-step explanation:

Resource allocation is the process of assigning a portion of a resource's capacity to a certain task. A resource can be in one of three states of allocation: under allocated, fully allocated, and over allocated.

When a resource is under allocated, it means that not enough of its capacity has been devoted to the task. When a resource is fully allocated, it means that its capacity is completely devoted to the task. And when a resource is over allocated, it means that more of its capacity has been devoted to the task than it is actually able to handle.

User Parcydarks
by
7.6k points
7 votes

Answer:

D. Under allocated, Fully allocated or Over allocated.

Step-by-step explanation:

  1. Under allocated: A resource is considered under allocated when it is not assigned enough work to utilize its full capacity, i.e., its capacity is not fully utilized.
  2. Fully allocated: A resource is considered fully allocated when it is assigned just the right amount of work to utilize its full capacity, i.e., its capacity is fully utilized.
  3. Over allocated: A resource is considered over allocated when it is assigned more work than its capacity, i.e., it is assigned more work than it can handle in the given time frame.

These states of allocation are important in project management to ensure that resources are optimally utilize