Answer:
B. "CTRL + F2".
Step-by-step explanation:
In Microsoft Project, there are different methods for creating task links, which represent the relationships between tasks in the project schedule. These methods include:
- A. Dragging tasks on each other: This method involves selecting the task you want to link and dragging it to the task it should be linked to. This will create a dependency link between the two tasks.
- B. CTRL + F2: This is not a valid method for creating task links in Microsoft Project.
- C. Link button on Task Bar: This method involves selecting the tasks you want to link and clicking the "Link Tasks" button on the Task tab in the ribbon. This will create a dependency link between the selected tasks.
- D. CTRL + SHIFT + F5: This method involves selecting the task you want to link and pressing the "CTRL + SHIFT + F5" keys. This will open the "Predecessors" column for the selected task, where you can enter the ID number of the task that should come before it.
Therefore, the correct answer is B. "CTRL