On January 2, 2010, York Corp. replaced its boiler with a more efficient one. The following information was available on that date:

Purchase price of new boiler
$150,000
Carrying amount of old boiler
10,000
Fair value of old boiler
4,000
Installation cost of new boiler
20,000
The old boiler was sold for $4,000. What amount should York capitalize as the cost of the new boiler?
A. $150,000.
B. $166,000.
C. $170,000.
D. $160,000.

User Cjhill
by
4.2k points

1 Answer

9 votes
D. $160,000.

:) LOL hoper this helped