Due to delays, a company had to extend a project from 64 days to 125 days. What was the percentage increase in time to complete the project? Round your answer to the nearest tenth.

1 Answer

5 votes

Answer:

195.3%

Explanation:

125/64 ~ 1.953

Around 195.3%.