if 20 men can complete a piece of work in 16 days how many men should be exiled to finish the work in 20 days? ​

1 Answer

3 votes

Answer: 16 men should be assigned to finish the work in 20 days.

Explanation:

Let's assume that the number of men needed to complete the work in 20 days is y. Then, the rate of work done by each man is given by 20/16=5/4 units of work per day.

So, the rate of work done by y men is given by 5/4 * y units of work per day.

Since the total work is constant, we have 20 men * 20/16 units of work per day = y men * 5/4 units of work per day.

Dividing both sides by 5/4, we get:

y = 20 * 20/16 / (5/4) = 20 * 4/5 = 16 men.

Therefore, 16 men should be assigned to finish the work in 20 days.