The WBS provides the basis on which resource assignments are made.

Group of answer choices

True

False

User Dokondr
by
7.5k points

1 Answer

2 votes

True. The Work Breakdown Structure (WBS) is a hierarchical decomposition of a project into smaller, more manageable tasks. It provides the framework for organizing and defining the total scope of a project and is used as the basis for resource assignments and budgeting.