If 12 workers clean up a certain stretch of the Jukskei river in 4 days, how long would it have taken to clean up this stretch if only 8 workers had been available? ​

User Ornella
by
7.4k points

1 Answer

2 votes

Answer:

6 days

Explanation:

12 workers will clean up in 4 days

how many days would it take 8 workers?

let the number of days be x

x=(12×4)/8

x= 6 days