209k views
2 votes
A project should take no more than 60 hours. If John can spare 7.5 hours per day to work on the project, what is the maximum number of days it will take him to finish

User IvanP
by
7.9k points

1 Answer

3 votes

Answer:

8 days

Explanation:

We know

A project should take no more than 60 hours, which means the number of hours should
\leq 60 hours.

John can spare 7.5 hours per day to work on the project.

Let x represent the number of days; we have the equation

7.5x
\leq 60

x
\leq 8

So, the maximum number of days it will take him to finish is 8 days.

User Shloimy
by
8.7k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories