Ohanna Lucy makes wooden boxes in which to ship motorcycles. Lucy and her three employees invest a total of 30

hours per day making the 200

boxes.
Part 2
​a) Their productivity

​boxes/hour. ​(Round your response to two decimal​ places.)
Part 3
Lucy and her employees have discussed redesigning the process to improve efficiency. Suppose they can increase the rate to 300
boxes per day.
​b) Their new productivity equals
​boxes/hour. ​(Round your response to two decimal​ places.)
Part 5
​c) The unit increase in productivity is enter your response here

​boxes/hour. ​(Round your response to two decimal​ places.)
Part 6
​d) The percentage increase in productivity is enter your response here
​%.
​(Enter your response as a percentage rounded to two decimal​ places.)


Riverside Metal Works produces cast bronze valves on a 12
​-person
assembly line. On a recent​ day, 200
valves were produced during
6
​-hour
shift.
Part 2
​a) Labour productivity
of the line
​valves/labour hour. ​(Round your response to two decimal​ places.)
Part 3
​b) The manager at Riverside changed the layout and was able to increase production
to 220
units per 6
​-hour
shift. The new labour productivity equals
​valves/labour hour. ​(Round your response to two decimal​ places.)
Part 4
​c) The percentage of productivity increase equals
enter your response here​%.
​(Round your response to one decimal​ place.)

User Ndifreke
by
7.3k points

1 Answer

4 votes

Answer: Question one:
a) 6.67 boxes/ hour
b) 10 boxes/ hour
c) 3.33 boxes/ hour
d) 49.93% increase

Explanation:

Question two:

a) 33.33 valves/ hour
b) 36.67 valves/ hour
c) 10.02% increase