36.6k views
4 votes
Shoring or shielding is used when:

A. The excavation has been made in Type C soil.
B. The excavation will be re-created as a trench at a later point.
C. Cost is an issue.
D. The location or depth of the cut makes sloping at the maximum allowable slope
impractical.

User XShirase
by
6.8k points

1 Answer

1 vote

Answer:

D. The location or depth of the cut makes sloping at the maximum allowable slope impractical.

User Tzar
by
7.4k points