60 workers can complete a work in 21 days. How long will it take to complete the some work if 10 more workers were added?​

1 Answer

1 vote

Answer:

Explanation:

set 1 is the work, then 60 works finish 1/21 per day.
(1)/(21*60) is the work for per workers. so, the days for 70 workers is
(21*60)/(70)=18 days.

it will spend 18 days to complete