20 workers can paint a building in 21 days. If work has to be finished in 15 days, find the number of extra workers required.

User Marcie
by
8.0k points

1 Answer

4 votes

Explanation:

20 workers finish work in 21 days.

the necessary work effort is 20×21 = 420 workdays.

the same effort is needed even if the overall time is shorter.

x workers in 15 days.

x × 15 = 420

x = 420/15 = 28 workers.

so, 28-20 = 8 additional workers are needed to finish the work in 15 days.