Answer:
Solution:
Step 1: Calculate the total contribution margin of the 2,000 units:
Total contribution margin = Unit contribution margin x Number of Units
Total contribution margin = $75.00 x 2,000
Total contribution margin = $150,000
Step 2: Calculate the total number of hours required for hardening treatment:
Total hours of hardening treatment = Hardening treatment hours per unit x Number of Units
Total hours of hardening treatment = 3 hrs x 2,000
Total hours of hardening treatment = 6,000 hrs
Step 3: Calculate the unit contribution margin per production constraint hour:
Unit contribution margin per production constraint hour = Total contribution margin / Total hours of hardening treatment
Unit contribution margin per production constraint hour = $150,000 / 6,000
Unit contribution margin per production constraint hour = $25.00