Answer:
6.67 hour per day
Explanation:
If
=8 hours a day = 12 days
then
= ? = 10 days
= 10/12 × 8hours per
= 6.67 hours per day.
9.6 hours
12×8 would equal the amount of hours it takes to complete the job in 12 days so you simply divide that number by 10 which will give you 9.6h