The time between completions of successive units on a production line is called:

A) cycle time.
B) takt time.
C) elapsed time.
D) work time.

User Jordan D
by
7.0k points

1 Answer

4 votes

Answer:

a

Step-by-step explanation:

the time between the completions of successive units on a production line is called cycle time. Hope this helps <33