If 10 men can complete a piece of work in 30 days how many men are requiredto complete the same job in 25 days?
asked
Nov 13, 2015
229k
views
2
votes
If 10 men can complete a piece of work in 30 days how many men are requiredto complete the same job in 25 days?
Mathematics
high-school
Jordan Miner
asked
by
Jordan Miner
8.4k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
3
votes
We must assume that all workmen work at the same rate, and keep it up forever.
More men ==> fewer days
so the proportion is: 30/25 = x/10
Cross-multiply the proportion:
300 = 25 x
Divide each side by 25 :
x = 300/25 =
12 men
Bobeff
answered
Nov 18, 2015
by
Bobeff
8.1k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.5m
questions
12.2m
answers
Other Questions
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Write words to match the expression. 24- ( 6+3)
A dealer sells a certain type of chair and a table for $40. He also sells the same sort of table and a desk for $83 or a chair and a desk for $77. Find the price of a chair, table, and of a desk.
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org