In a certain week, a production schedule for a certain department shows the following parts being produced: 540 parts of type A, 1200 parts of type B, 490 parts of type C, and 780 parts of type D. The respective production times for these parts are the following: TpA = 5.28 min, TpB = 2.86 min, TpC = 4.65 min, and TpD = 3.22 min. Determine the workload for this department in hours per week.

User QuinRiva
by
4.9k points

1 Answer

5 votes

Answer:

about 185 hours per week

Step-by-step explanation:

It is convenient to let a spreadsheet form the sum of products. The total is in minutes, so needs to be divided by 60 to get hours.

About 185 hours per week are required for the given production schedule.