The number of hours required to do a painting job is represented by the function f(x)=2x , where f(x) gives the number of hours and x is the number of painters doing the job. How much time will {4, 10, 14, 16, 18} workers take to do the job?

User Guile
by
7.1k points

1 Answer

0 votes
4. 8
10. 20
14. 28
16. 32
18. 36