50 men working 10 hours daily can complete a job in 20 days. In how many days can 80 men do the job if the working hours are reduced by 50%. A. 20 days B. 18 days C. 25 days D. 28 days #wrong answers wil
asked
Jul 13, 2022
45.1k
views
14
votes
50 men working 10 hours daily can complete a job in
20 days. In how many days can 80 men do the job if
the working hours are reduced by 50%.
A. 20 days
B. 18 days
C. 25 days
D. 28 days
#wrong answers wil reported
Mathematics
college
Sagar Chilukuri
asked
by
Sagar Chilukuri
8.0k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
11
votes
Given :-
50 men do 10 hours work daily complete work in 20 days
80 men do job in 50% time
To Find :-
Days required
Solution :-
1 man may do job in (50 × 20) days =
1 man may do job in 1000 days
Now,
80 man = 1000/80 = 12.5
Now,
When hours reduced 50% then we will multiply days by 2
Total days = 12.5 × 2 = 25 days.
Hence
Option C is correct
Dipiks
answered
Jul 20, 2022
by
Dipiks
8.0k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
8.9m
questions
11.6m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org