Six people to can perform a task in 8 days. If we add 2 equally able people, how long would it take?

User Yuh
by
7.1k points

2 Answers

4 votes

Answer:

6 days

Explanation:

User Kishieel
by
7.3k points
4 votes
1 man does 1/48th piece of work per day
then 8 man do 1/6th piece of work per day
so they can do the work in 6 days