230k views
4 votes
Patty and Mike are installing new floors in their house. Working alone, Mike can complete the floor in 10 hours. Patty can complete the same floor in 8 hours if working alone. How long will it take them, working together, to finish the floor? Round your answer to the nearest hundredth if necessary.

9 hours
0.23 hours
4.44 hours
18 hours

User Gluxon
by
6.3k points

2 Answers

4 votes

Answer:

Explanation:

Alright, lets get started.

In 10 hrs, Mike can complete the of floor = 1

So, 1 hr, Mike can complete the part of floor =
(1)/(10)

In 8 hrs, Patty can complete the floor = 1

So, 1 hr, Patty can complete the part of floor =
(1)/(8)

So, in 1 hrs, they both will work together to complete the floor =
(1)/(10)+(1)/(8)

=
(8+10)/(80)

=
(18)/(80)

So, they both cmplete 18/80 part in = 1 hrs

So, they both will complete 1 part is =
(1)/((18)/(80) )

So, they both will complete 1 part is =
(80)/(18)=4.44

So, it will tae 4.44 hrs to finish the floor. : Answer

Hope it will help :)

User Isvforall
by
7.0k points
0 votes
There are several important information's already given in the question. Based on those information's the answer can be easily deduced.

Time taken by Mike to complete the flooring alone = 10 hours
Time taken by Ratty to complete the flooring alone = 8 hours
Then
Time taken by both of them working together = (10 * 8)/(10 + 8)
= 80/18
= 4.44 hours
From the above deduction, it can be easily concluded that the correct option among all the options that are given in the question is the third option or the penultimate option.
User Alex Howell
by
7.1k points