I need some help with this calculus assignment Second part is How much is spent on the job from the 12th to the 20th day

I need some help with this calculus assignment Second part is How much is spent on-example-1
User Nashr Rafeeg
by
2.8k points

1 Answer

7 votes
7 votes

rate of change = f(x) = 4.1x + 1.9

Since we want the total expenditure if the job takes 12 days, we must integrate the expression above from 0 to 12. Like this:


\text{Total expenditure=}\int f(x)dx\text{ from x = 0 to x = 12}
\begin{gathered} \int ^{^(12)_{}}_04.1x+1.9dx \\ =(4.1x^2)/(2)+1.9x\rbrack^(12)_0= \\ =(4.1)/(2)(12^2-0^2_{})+1.9(12-0)= \\ =4.1*72+1.9*12= \\ =295.2+22.8= \\ =318 \end{gathered}

So our final answer is:


\text{Total expenditure=318}