8 construction workers can build a house in 60 days. After working for 12 days, 4 more workers join in to build the house. How many days will they take to build the rest of the house?

Please show all workings and explain. Thanks! :)

[50 Points] 8 construction workers can build a house in 60 days. After working for-example-1
User XAnguera
by
6.9k points

1 Answer

5 votes
Solution in the attachment.

Answer: 32 days.