george completed 3/5th of work in 9 days with the help of paul he completes remaining work in 4 days.In how many days paul alone can finish the work

User Leetom
by
8.0k points

1 Answer

0 votes
If George completed 3/5 of work in 9 days, it means that he needs 3 days to finish 1/5th of the work.

The remaining part is 2/5 because 1-3/5=2/5. 2/5 is also 6/15

From this, how much did George do? in the first 3 days he did 1/5th and then one more day was left, during which he did 1/5/3=1/15th.

So he did in total 1/15+1/5=1/15+3/15=4/15.
this means that Paul did the rest of 6/15, so Paul did 6/15-4/15=2/15.

So we know that he does 2/15 in 4 days, which means that every two days he can do 1/15 of the work

so he would need 15 times 2 days to finish the work - 30 days!