Anita can paint the shed in 5 h. If Kris helps her, they can paint the shed in 3 h. How long will it take Kris to paint the shed alone?

User Nau
by
8.4k points

1 Answer

3 votes
Anita can paint the shed in 5 hours. If Kris helps her, they can paint the shed in 3 hours. How long would it take Kris to paint the shed alone?
----
Anita rate = 1/5 job/hr
Together rate = 1/3 job/hr
Kris rate = 1/x job/hr
Equation:
rate + rate = together rate

1/x + 1/5 = 1/3
----
Multiply thru by 15x to get:
15 + 3x = 5x
2x = 15
x = 7.5 hrs (time for Kris to do the job alone)