a contractor hired 150 men to pave a road in 30 days how many men would he hire to do the same work in 10 days​

User Mochidino
by
2.9k points

1 Answer

6 votes

Answer:

750 men

Explanation:

150 divided by 3 equals 5

5 times 150 equals 750

so it will take 70 men in 10 days