If your company needs to produce 7,800 products by the end of the next 12 weeks, how many products will you need to produce each week to finish on schedule?

User CmdrSharp
by
7.9k points

1 Answer

6 votes

The company will have to produce at least 650 products each week to achieve 7800 products in 12 weeks


(7800 products divided by 12weeks = 650 products per week)