Using new equipment, a worker finished 4 more parts in an hour than was planned and fulfilled his daily task not in 8 hours but in 6 hours. How many parts did the worker had to finish that day according to schedule? I really need help and ASAP I beg plz

User TJ Thind
by
5.5k points

1 Answer

3 votes
4 parts finished for 1 hour and worked for 6 hours so the no of parts fulfilled that day is: 4x6=24 parts