The first painter can finish a paint job in 2 hours. The second painter can finish the same job in 8 hours. How long would it take them to finish the job if they were working together?

User Cjg
by
7.5k points

2 Answers

0 votes

Answer:

1 3/5 hr

Explanation:

User Ivan Smetanin
by
8.5k points
2 votes
I believe it takes 1 3/5 hrs for them to finish the job together