Sam constructs 3/4 of the wall in 1 2/3 days. How many days will he need to construct the wall? Simplify your answer and write it as a proper fraction or as a whole or mixed number. Sow your work.

2 Answers

2 votes
5/3 days for 3/4 of Wall, so
5/3*4/3 days for 3/4*4/3 = 1 Wall
Or 20/9 (2_2/9) days.
User MarchalPT
by
8.2k points
7 votes
3/4w=5/3
=> w=5/3*4/3=20/9=2 1/9 days