Laura is carefully estimating the time required for each phase of a proposed system development project to see if her company can meet the client's desired time for completion. laura is checking on ___________.

1 Answer

7 votes
Laura is checking on schedule feasibility.
She is doing everything in order to see whether each phase will run smoothly and according to her schedule. She wants to see if her schedule is possible at all, which is why she is making a timetable to prove her hypotheses.