Answer:52 min
Explanation:
Given
5 people paint 5 walls in 52 minutes
Now if 1 person paints the 5 walls then time required will be 5 times more
1 Person paint 5 walls in

For 20 walls person has to do 4 times the previous walls
1 person paints 20 walls in

For 20 People time required will be 20 times less
i.e.